The realization of the 2nd geothermal heat doublet Trias Westland has been fill in . With assure the financing for this doublet and the expanding upon of the hotness internet , the first contracts with the drilling company , contractor and suppliers have been signed .
The greenhouse horticulture ship’s company colligate with Trias Westland that were unable to employ the heat from the first doublet now also have approach to sustainable heat through this exploitation . The enlargement of Trias Westland offers a significant increase in sustainability for Westland glasshouse horticulture , like to the natural gas usance of around 15,000 households . The step follows the beginning of output with the first doublet on July 15 of this year .
Preparation work for the realization of the 2nd geothermic warmth doublet on the Lange Broekweg in Naaldwijk will bulge out in the first stern of 2020 . The grammatical construction of the heat mesh will start directly .

New entrantsIn 2017 , 49 Westland greenhouse horticulture enterpriser joined force and invest themselves to the development of Trias Westland , an innovative geothermic oestrus undertaking to make greenhouse horticulture in Westland more sustainable . Now , more than two years afterward , with the commissioning of the first doublet in July 2019 , 26 connected participant receive heat from a geothermic heat root in the Lower Cretaceous layer at a depth of 2.3 kilometers .
At the request of the nursery entrepreneurs , the initiator of Trias Westland - HVC , Capturam and Royal FloraHolland - investigated the possibilities for further utilisation of heat by realizing a second doublet in Naaldwijk . The achieved financial close will also start the other participating greenhouse growers , include various newfangled entrants , to supply their businesses with sustainable heating .
fiscal participationAfter obtaining the SDE+ subsidy for a 2d doublet at the same position , exertion were made to secure funding . To further involve the player in the Trias Westland projection , a construction has been devised to offer participating caller the chance to participate in the risk - have a bun in the oven part of the financing . A issue of participant have decided to contribute to the funding .
fiscal closeAll parties have been contracted and Rabobank and BNG Bank collectively lead the bank funding . Just like Trias Westland 1 , the expanding upon will be financed on the base of " non - recourse project funding " . That is , a loan in which the banking company is only entitled to repayment from the issue of the project , without liability of shareholders or third party . That is why the banks soundly investigated the engineering and financing of the integrated Trias Westland project in advance .
Expansion heat networkPart of the new development is also the expanding upon of the heat electronic web of Trias Westland , whereby a large part of this web function as the primary line within the Westland Heat System ( WSW ) , the regionally planned heating system web in the Westland . Trias Westland has received a subsidy of 3.77 million euros for this from the Ministry of Agriculture , Nature and Food Quality . This support was already announced in the Climate Agreement .
The itinerary cogitation of the heat web have largely been completed and work out based on the sign agreements of the participant . The first whole kit and caboodle on the Kasteelweg in Naaldwijk will startle at the beginning of September so that they can be combined with the planned restoration from the municipality of Westland . Over the next six months , two kilometre of estrus line will be installed in stages .
Trias Westland is an initiative of HVC , Capturam , Royal FloraHolland and a large group of greenhouse entrepreneurs . These mate attach great grandness to sustainability and see geothermal energy as an important alternative to natural gas .
For more information : Trias Westlandwww.triaswestland.nl